Last phase of South Pars Gas Field to start production soon

The development of the giant South Pars Gas Field’s Phase 11 is underway and the phase will soon become operational, managing director of the National Iranian Oil Company said.

7 December 2022
ID : 44283
Share
Share with
Telegram Whatsapp
Link

The development of the giant South Pars Gas Field’s Phase 11 is underway and the phase will soon become operational, managing director of the National Iranian Oil Company said.

“The drilling of the last four wells in the phase is in the final stages and after the project’s subsea pipe-laying operations are completed, gas extraction will begin in the near future,” the Oil Ministry’s news agency Shana also quoted Mohsen Khojastehmehr as saying.

Phase 11 is the only one among the 24 phases of the joint field in the Persian Gulf, which has not been developed yet. Iran shares the field with Qatar.

The Phase 11 development project included the construction and installation of the jackets and topsides of the phase, drilling 12 wells and laying 115-km-long 32-inch pipelines to transfer mono-ethylene glycol and liquefied natural gas to onshore plants for processing.

The location of South Pars Phase 11 is seen in the image. 

About 12,000 meters of drilling operations to dig four production wells have been carried out and it is estimated to reach 15,000 meters upon completion.

An estimated 14 million cubic meters of natural gas per day will be extracted from the phase initially.

A total of $15 million have been invested in the phase and an additional $70 million are needed to complete the project. 

When it becomes fully operational, the phase will produce 56.6 million cubic meters of gas per day, plus 75,000 barrels of gas condensate, which will be transferred to refineries in Asalouyeh and Kangan in Bushehr Province.